Blog

1120 of 119 items

Ministry Expansion Update for June 13, 2019

by CMPC

Here’s what has happened in the last weeks: Work continues on the new site lights in the parking lot—including demolition for the islands and construction of the bases Sprinkler installation continues in the Shaker Drive addition and has also spread to the preschool rooms Work continues on the EFIS (the bands above and below the […]

Treats and Sweets 2019

by CMPC

Fourteenth Annual Treats & Sweets a Success Duets, choirs, soloists, bands, and quartets. Handcrafted artwork, cakes, fashion items, and a staycation package. Tastings, dinners, and culinary trips. This—and a whole lot more—was offered on Sunday evening June 9, at CMPC’s annual Musical Treats & Sweets fundraiser in the sanctuary. Over $5,000 was raised to help […]

Ministry Expansion Plan Update for May 30, 2019

by CMPC

Here’s what has happened in the last week: Work continues on the new site lights in the parking lot Sprinkler installation continues in the Shaker Drive addition Work continues on the EFIS (the bands above and below the Hardie board on the exterior of the building) The work will begin on installing the new roofs […]

Ministry Expansion Plan Update for May 23, 2019

by CMPC

Here’s what has happened in the last week: The baseboard was installed in the sanctuary Work continues on the new site lights in the parking lot The storm drain between Shaker Drive and the church was installed The stairs closest to the sanctuary and the wooden exit stairs out of Fellowship Hall have been removed […]

Ministry Expansion Plan for May 16, 2019

by CMPC

Here’s what has happened in the last week: Work has begun on the new site lights in the parking lot The storm drain between Shaker Drive and the church building is being installed Work has begun on demolishing the stairs closest to Fellowship Hall, the wooden exit stairs, and the windows in Fellowship Hall Sprinkler […]

Ministry Expansion Plan Update for May 9, 2019

by CMPC

Here’s what has happened in the last week: The concrete for the stairs in the new entrance was poured The walls were cut for the new passageways between the downstairs hallway and the new Shaker drive addition, between the lower level of the new Shaker Drive addition and the old choir robing room, and between […]

CMPC Participates in Rebuilding Together Howard County

by CMPC

On Saturday, April 27th nine members of CMPC participated in the Rebuilding Together Howard County workday.  Led by team leader Brent Jones, Philip Davies, Glenn Del Favero, Maddie Del Favero, Josh Gliptis, Scott Hoffman, John McPherson, Wes Millard, and Michael Schreiber worked a full day to complete multiple projects around the home of our “neighbor” Mary.  […]

Ministry Expansion Plan Update for May 2, 2019

by CMPC

Here’s what has happened in the last week: The drywall in the new entrance was completed Work has begun on the stairs in the new entrance The floor protection in the sanctuary was removed and the carpet thoroughly cleaned The sheathing was added to the new Shaker Drive addition roof The new light switches were […]

Ministry Expansion Plan Update for April 25, 2019

by CMPC

Here’s what has happened in the last week: New lights were installed in the sanctuary Framing of the new exterior and interior walls in the Shaker Drive addition is complete The roof trusses were added to the Shaker Drive addition Hardie board was installed on the exterior of the new entrance and on the exterior […]

Ministry Expansion Plan Update for April 18, 2019

by CMPC

Here’s what has happened in the last week: New lights are being installed in the sanctuary More steel beams were set in the Shaker Drive addition Framing of the new exterior and interior walls in the Shaker Drive addition is underway Hardie board is being installed on the exterior of the new entrance and on […]