Here’s what has happened in the last weeks:
- Grading work has begun around the Shaker Drive addition and will continue to include the new location of the playground
- Drywall is up almost entirely in both levels of the Shaker Drive addition
- Work continues on restoring the lower level restrooms (near the church office)
- More curbs have been poured as have the new sidewalks
- The portion of the ceiling in fellowship hall that was demolished has been reframed and drywall has been hung
- The prep work on the subfloor in the new addition is just about done
- The drop ceiling in the downstairs hallway has been installed
- Most of the roofing has been completed
- The new vent hood for the kitchen was installed
- The new floor in the kitchen has been laid
- Work continues on the new driveway
Here’s what is scheduled to happen in the next week (or so):
- The hold opens will be installed for the new doors at the top of the new stairs
- Work will begin on finishing the classroom across from the pastor’s office
- The new floor will be laid in the office/classroom hallway
- Floor tile will be laid in the new bathrooms and in the lower level of the Shaker Drive addition
- The kitchen appliances and other equipment will be delivered and installed
Keep checking back here regularly for updates. If you have questions please feel free to reach out to Pastor Scott at pastor.hoffman@cmpcusa.org.