Here’s what has happened in the last weeks:
- Work continues on the new site lights in the parking lot—including demolition for the islands and construction of the bases
- Sprinkler installation continues in the Shaker Drive addition and has also spread to the preschool rooms
- Work continues on the EFIS (the bands above and below the Hardie board on the exterior of the building)
- Roofing was installed on the sanctuary and new Shaker Drive addition
- Demolition work continues in Fellowship Hall
- Grading work has begun around the Shaker Drive addition and will continue to include the new location of the playground
- The tile floor for the new entrance was completed and now carpet is going in inside the new doors
- The upper level floors at the old stair locations were infilled
- The rest of the framing of the stage in Fellowship Hall (including the ramp) is complete
- Drywall is going up in both levels of the Shaker Drive addition
Here’s what is scheduled to happen in the next week (or so):
- Work will continue on restoring the lower level restrooms (near the church office)
- Some of the drop ceiling will be finished in the downstairs hallway
- More curbs will be poured
- Roofing work will continue
- Sprinkler pipes will be installed throughout the area under the sanctuary
- The hold opens will be installed for the new doors at the top of the new stairs
- The walls of the new Shaker Drive addition will be primed and painted
- The new vent hood for the kitchen will be installed
- Work will begin on the new flooring in the Shaker Drive addition
Keep checking back here rergularly for updates. If you have questions please feel free to reach out to Pastor Scott at pastor.hoffman@cmpcusa.org.