Here’s what has happened in the last week:
- New lights were installed in the sanctuary
- Framing of the new exterior and interior walls in the Shaker Drive addition is complete
- The roof trusses were added to the Shaker Drive addition
- Hardie board was installed on the exterior of the new entrance and on the exterior of Fellowship Hall
- The foundation for the new entrance was backfilled and the fence closest to the temporary entrance removed
- Some sprinkler pipes have been installed in Fellowship Hall with more to come
- The connection to the new water main has been made
Here’s what is scheduled to happen in the next week (or so):
- The drywall will be completed in the new entrance
- Painting in the new entrance will begin
- The new stairs will be added to the new entrance
- The floor protection in the sanctuary will be removed and the carpet thoroughly cleaned
- The pews will be reinstalled in the sanctuary
- The sheathing will go on the new Shaker Drive addition roof
- Work has begun and will continue on the church office, pastor’s office, and one classroom so as to complete those rooms and allow for the church offices to move back onsite
Keep checking back here each week for updates. If you have questions please feel free to reach out to Pastor Scott at pastor.hoffman@cmpcusa.org.