Here’s what has happened in the last week:
• The celling in the sanctuary was patched in and the final coat of skimcoat was applied
• The roof membrane was installed on the new entrance
• The most recent round of asbestos abatement outside fellowship hall was completed
• A new construction entrance was cut in off of Shaker Drive
• The curbs for the new driveway were poured
• One of the openings to the new Shaker Drive addition was cut in
• Work continues on the walls of the Shaker Drive addition
• Some of the steel beams for the Shaker Drive addition were set in place
• Work continued on the new HVAC units in the rooms underneath fellowship hall
Here’s what is scheduled to happen in the next week (or so):
• New lights will be installed in the sanctuary
• Waterproofing will be added to the new Shaker Drive addition walls
• The remaining steel beams and columns will be installed in the new Shaker Drive addition
• Painting will begin in the sanctuary
• Insulation will be added to the new entrance.
• Drywall will go up in the new entrance
• The slab for the new shaker drive addition will be poured
• Stone will be laid along the new driveway
Keep checking back here each week for updates. If you have questions please feel free to reach out to Pastor Scott at pastor.hoffman@cmpcusa.org.