Ministry Expansion Plan Update for September 19, 2019

by CMPC

Here’s what has happened in the last weeks: The remaining light poles are being installed The curb on the southside of the parking lot was poured The sidewalk from the new emergency stair to the parking lot was poured Here’s what is scheduled to happen in the next week (or so): The parking lot will […]

Ministry Expansion Plan for September 12, 2019

by CMPC

Here’s what has happened in the last weeks: CMPC volunteers worked hard to clear out the final storage container The remaining light poles are being installed The curb on the southside of the parking lot is being poured Here’s what is scheduled to happen in the next week (or so): The sidewalk from the new […]

Ministry Expansion Plan for September 5, 2019

by CMPC

Here’s what has happened in the last weeks: The flooring has been laid throughout the building We have passed some final inspections The bioretention area in the parking lot is complete CMPC volunteers worked hard to clear out 3 of the 4 storage containers The top layer of asphalt was added to the new driveway […]

News from the Wellers

by CMPC

Dear Friends, Since we returned from the US in Oct we have been busy amidst many challenges. I should probably go back and recount all that has happened, but that would probably make for a very long letter. Michael has been teaching at the two Bible Schools run by the two synods in Gambella. Both […]

Ministry Expansion Plan for August 22, 2019

by CMPC

Here’s what has happened in the last weeks: The water service was switched over to the new water main and the water was tested The electrical and plumbing connections in the kitchen are almost complete Carpet has been laid between the top of the new stairs and the entrance to the sanctuary The remaining playground […]

Ministry Expansion Plan for August 14, 2019

by CMPC

Here’s what has happened in the last weeks: The new playground equipment was installed along with the rubber ground covering The driveway was paved and will receive the final coat soon The carpet has been laid in the nursery and fellowship hall The flooring has been laid on the stage in fellowship hall and in […]

Ministry Expansion Plan for July 31, 2019

by CMPC

Here’s what has happened in the last weeks: Work continues on the fire protection system throughout Work has begun on the new playground installation The drop ceiling is almost complete throughout the new addition The sprinklers have been installed in the area under the sanctuary The classrooms/meeting rooms under the fellowship hall have been completed […]

Ministry Expansion Plan for July 17, 2019

by CMPC

Here’s what has happened in the last weeks: The new kitchen appliances have been delivered Some of the floor and wall tiles have been installed in the restrooms New doors have been hung throughout the new Shaker Drive addition Stairs have been added in the lower level of the Shaker Drive addition Work continues on […]

Mars Hill 2019

by CMPC

For six hot days in July, sixteen people (children, youth, and adults) from CMPC met up with 49 other folks (from churches in Bowie, MD and Pittsburgh, PA) to serve brothers and sisters in need in Madison County, North Carolina.  Partnering with a local organization called The Community Housing Coalition the volunteers from three churches […]

Ministry Expansion Plan for July 3, 2019

by CMPC

Here’s what has happened in the last weeks: Grading work has begun around the Shaker Drive addition and will continue to include the new location of the playground Drywall is up almost entirely in both levels of the Shaker Drive addition Work continues on restoring the lower level restrooms (near the church office) More curbs […]