Posts from May 2019

6 Items

Ministry Expansion Plan Update for May 30, 2019

by CMPC

Here’s what has happened in the last week: Work continues on the new site lights in the parking lot Sprinkler installation continues in the Shaker Drive addition Work continues on the EFIS (the bands above and below the Hardie board on the exterior of the building) The work will begin on installing the new roofs […]

Ministry Expansion Plan Update for May 23, 2019

by CMPC

Here’s what has happened in the last week: The baseboard was installed in the sanctuary Work continues on the new site lights in the parking lot The storm drain between Shaker Drive and the church was installed The stairs closest to the sanctuary and the wooden exit stairs out of Fellowship Hall have been removed […]

Ministry Expansion Plan for May 16, 2019

by CMPC

Here’s what has happened in the last week: Work has begun on the new site lights in the parking lot The storm drain between Shaker Drive and the church building is being installed Work has begun on demolishing the stairs closest to Fellowship Hall, the wooden exit stairs, and the windows in Fellowship Hall Sprinkler […]

Ministry Expansion Plan Update for May 9, 2019

by CMPC

Here’s what has happened in the last week: The concrete for the stairs in the new entrance was poured The walls were cut for the new passageways between the downstairs hallway and the new Shaker drive addition, between the lower level of the new Shaker Drive addition and the old choir robing room, and between […]

CMPC Participates in Rebuilding Together Howard County

by CMPC

On Saturday, April 27th nine members of CMPC participated in the Rebuilding Together Howard County workday.  Led by team leader Brent Jones, Philip Davies, Glenn Del Favero, Maddie Del Favero, Josh Gliptis, Scott Hoffman, John McPherson, Wes Millard, and Michael Schreiber worked a full day to complete multiple projects around the home of our “neighbor” Mary.  […]

Ministry Expansion Plan Update for May 2, 2019

by CMPC

Here’s what has happened in the last week: The drywall in the new entrance was completed Work has begun on the stairs in the new entrance The floor protection in the sanctuary was removed and the carpet thoroughly cleaned The sheathing was added to the new Shaker Drive addition roof The new light switches were […]