Here’s what has happened in the last weeks: The remaining light poles are being installed The curb on the southside of the parking lot was poured The sidewalk from the new emergency stair to the parking lot was poured Here’s what is scheduled to happen in the next week (or so): The parking lot will receive the final seal coat and parking…